Projects

Reconstruction from industrial building to three stars hotel

Customer: CJSC “Concern Achemos Grupe”;
Completed operations characteristics: reconstruction from industrial building, the Hotel for 162 visitors, building area 3.350 m2;
Completion date: 2008 12.

_DID1079-.jpg

Reconstruction from industrial building to administrative building

Customer: CJSC “Projektu centras”;
Reconstruction of the building 5E2/b into the administrative building, Total area: 2.012 m2;
Designer: CJSC “Projektu centras” ;
Contractor: CJSC “Sienojus”;
Construction Technical supervision: CJSC “Projektu centras”;
Completion date: 2009 01.

Reconstruction of oils production economics

Customer: CJSC “Okseta”;
Completed operations: preliminary design;
Completion date: 2008.

Creation of engineering facility

Customer: Administration of Kėdainiai district government;
Completed operations: basic design;
Completed operations characteristics: superintendence territory area – 84.277 m2, road length – 2.894 m, total water-supply network length – 5.538 m;
Completion date: 2008.

New construction of boiler house

Customer: CJSC “SCANDYE”;
Completed operations:
basic and detail design;
Completed operations characteristics: steam boiler with the capacity of 12 t/h, water heating boiler with the capacity of 1,5 MW, total capacity 9,7 MW;
Completion date: 2007.

Ukmerge birch peel factory

Customer: CJSC “Likmere”;
Completed operations characteristics: industrial building – 9.504 m2, administrative building– 654 m2, factory reprocess 150.000 m3 wet peel per year;
Completion date: 2008 11.

Reconstruction from industrial building to administrative building

Customer: CJSC “Projektu centras”;
Total area: 2.132 m2;
Designer: CJSC “Projektu centras”;
Contractor: CJSC “Jonavos ranga”;
Completion date: 2006.

Reconstruction from industrial building to three stars hotel

Customer: CJSC “Concern Achemos Grupe”;
Project are proceeding “from idea to keys”, the Hotel for 162 visitors, total area: 3.350 m2;
Designer: CJSC “Projektu centras”;
Contractor: CJSC “Sienojus”;
Completion date: 2008.

_MG_5437.jpg

Teaching center for JSC „Achema”

Customer: CJSC “Achemos mokymo centras” ;
Project are proceeding “from idea to keys”, total area: 2.200 m2;
Designer: CJSC “Projektu centras” ;
Contractor: CJSC “Projektu centras” ;
Construction Technical supervision: CJSC “Projektu centras”;
Completion date: 2008 11.

Reconstruction of the construction of industrial facilities

Customer: SC “Gliukoze”;
Project manager: CJSC “Projektu centras”;
Completion date: 2006 09.

Manufactory of natium, phosphorus, kalium (NPK) manures

Customer: SC “Achema”;
Total area: 16 ha;
Designer: CJSC “Projektu centras” and “Ceamag Giprodvigatel”;
Project manager: CJSC “Projektu centras”;
Completion date 2007.

Container for CO2, “Aldaris”, Latvia

Customer: SC "Achema" subsidiary company "Gaschema" ;
Designer: CJSC “Projektu centras”;
Completion date: CJSC “Projektu centras”.

02-Agromax-Vilkav0005a.jpg

Agro centre of Vilkaviskis

Customer: CJSC “Vilkaviskio agrochemija”;
Total area: 8,4 ha;
Designer: CJSC “Projektu centras”;
Project manager: CJSC “Projektu centras”;
Contractor: CJSC “Laugina”;
Completion date: I stage – 2007-01, II stage – 2007-10.

Agro centre of Vidukle

Customer: CJSC “Agrochemos mazmena”;
Total area: 7,9 ha;
Designer: CJSC “Projektu centras”;
Project manager: CJSC “Projektu centras”;
Contractor: CJSC “Sienojus”;
Completion date: I stage – 2008-09.

Container for CO2, “Saku”, Estonia

Customer: SC "Achema" subsidiary company "Gaschema";
Total area: 0,02 ha;
Designer: CJSC “Projektu centras” and “Sweco”;
Project manager: CJSC “Projektu centras”;
Completion date: 2008.

Previuos 1 2 3 4 ... 5 Next